2026-11-26
Rockwell lists PowerFlex 70 catalog numbers as End of Life with discontinued dates of 1 December 2026, 30 May 2027 or 1 July 2027, depending on the exact catalog number. This article gives the verified dates and ratings for seven catalog numbers, explains what End of Life and Engineering Replacement mean in practice, and ends with a checklist for spares and migration planning.
Read note →2026-11-25
Siemens phased out the rack PCs SIMATIC IPC647E (2U) and IPC847E (4U) on 1 October 2026. New units stay orderable until type cancellation on 1 October 2027, and the successor Rx-528A and Rx-548A platforms split by workstation and server roles.
Read note →2026-11-24
On 1 October 2026, Siemens announced the phase-out (PM400) of a range of ET 200 PROFIBUS interface modules; new parts stay orderable until 1 October 2027. This article checks the SIOS announcement line by line — what is covered, the PROFINET successors, and how to plan from here.
Read note →2026-11-23
Siemens phased out the SIMATIC IPC627E and IPC677E on 1 October 2026. New units stay orderable until 1 October 2027, but the spare parts and service commitment runs only five years, to 1 October 2032 — half the cover PLC users usually plan by.
Read note →2026-11-22
The spare-parts cabinet tells the story before any memo does. In a process plant running a redundant S7-400H station, the shelf holds two CPUs, a spare memory card and a CP 443-1, and someone has already written the station's tag numbers on masking tape. That cabinet is the reason Siemens' latest phase-out announcement matters: the S7-400 is not a controller you swap on a whim, and the parts on that shelf now have a fixed calendar.
Read note →2026-11-21
Four dates decide the SINAMICS S120 Combi Frame Type A retirement: phase-out announced 1 October 2025, last new-part orders 30 September 2026, product cancellation 1 October 2026, and repair and spare-parts support scheduled to run until 1 October 2035. The newer Frame Type B remains on sale, but Siemens states that hard substitution between FTA and FTB is not available.
Read note →2026-11-20
Siemens announced the phase-out (P.M400) of SINAMICS S120 Chassis-2 and Cabinet Modules-2 on 1 October 2026, covering 78 article numbers at 315 to 900 kW — with no successor, cancellation date or last-order date named. What owners should count now.
Read note →2026-11-19
Can you still buy a TeSys T motor controller from Schneider Electric — and if the one in your MCC bucket trips tonight, what exactly do you put in its place?
Read note →2026-11-18
Open a control panel on a line that has run for fifteen years and you will probably find it on the left end of a POINT I/O rack: a grey module with a two-digit node display, five screw terminals on a cream-coloured block, and a label that reads 1734-ADN. It is the adapter that ties up to 63 POINT I/O modules to a DeviceNet network, and it has done that job, quietly, for more than two decades. On 31 December 2026, Rockwell Automation stops selling it — and Rockwell names no replacement.
Read note →2026-11-17
Siemens has finished the drive platform it started with the G220 in 2023. For plants running G120 drives, the news changes nothing this week — and that is exactly why it is worth reading now, before the next project forces a choice.
Read note →2026-11-16
Three dates decide this one. On 15 November 2026, OMRON stopped taking new orders for the LD-60, LD-90, LD-90x and LD-250 autonomous mobile robots in Europe. On 31 December 2026, the last of those robots ships. And on 30 June 2032, OMRON closes maintenance support.
Read note →2026-11-15
A maintenance engineer in Ontario opens the spares cabinet and counts the Quantum CPUs on the shelf. One 140CPU65160, bought years ago as insurance against a failure that never came. The rack beside it has run since the plant was built, and the CPU inside it has not been orderable for years. None of that changes on 31 December 2026. What changes is quieter: on that date, under Schneider Electric's Canadian lifecycle record, standard manufacturer service — repair and spare-parts support — ends for three Quantum 140 CPUs at once. The shelf spare is still a spare. The question is whether the plant knows exactly which references it holds, and what replaces them when the next failure comes.
Read note →2026-11-14
Rockwell ends the Compact GuardLogix 5370 safety controllers on 31 December 2026. The expensive part of moving to 5380 is not the controller — it is the I/O beside it.
Read note →2026-11-13
Can I still order the IM 155-6 PN ST after September 2027 — and will the new IM 155-6 ST just drop into my ET 200SP station?
Read note →2026-11-12
Four dates decide this one. Siemens announced the phase-out of four SIMATIC S7-1500 and ET 200MP system power supplies on 1 October 2026, and the order window stays open for almost another year — but three of the four replacement part numbers do not exist yet as orderable stock.
Read note →2026-11-11
Siemens put the SIMATIC S7-1200 Generation 1 into phase-out on 1 November 2026. New G1 units stay orderable until 1 October 2027 — after that, only spare parts, for about ten years. What to check before you order, and how to migrate to G2.
Read note →2026-11-10
Hanwha Ocean and ABB signed a pact on 5 November 2026 to develop floating data centers — and the power behind them will come from proven platforms, not new inventions.
Read note →2026-11-09
Siemens cancelled the MICROMASTER 440 on 1 October 2019. If one still runs your line, check the full order number before you order a spare or a SINAMICS G120.
Read note →2026-11-08
ABB's own ramp-down announcement moves the DCS800 from Classic to Limited on 1 January 2027. New units have not been orderable since the end of 2022 — here is what the phase change actually takes away, what ABB has not yet specified, and what to check on installed drives before then.
Read note →2026-11-07
ABB's own lifecycle statement keeps the ACS310 and ACS355 in the Limited phase until 31 December 2026 — after that they are Obsolete. Here is what changes on 1 January 2027, which replacement each drive actually has, and what to line up before then.
Read note →2026-11-06
OMRON has set the final order date for the CJ2M-CPU3[] and CJ2H-CPU6[]-EIP at the end of March 2027 — here is exactly which models are affected, which are not, and what to line up before the window closes.
Read note →2026-11-04
Festo ADVC/AEVC short-stroke cylinders will no longer be available after 31 December 2026. Most mid-size variants have a named ADN-S/AEN-S successor, but 102 listed part numbers — including every Ø80 and Ø100 model — have none.
Read note →2026-11-03
WAGO PFC100 Generation 1 controllers 750-8100, 750-8101 and 750-8102 reached end of sale on 30 June 2026, with end of delivery on 16 December 2026. What the dates mean, the successor list from the discontinuation notice, and the cabinet checklist before the delivery window closes.
Read note →2026-11-02
Schneider Electric has retired the Modicon Premium and Quantum PLC lines and the Altivar 61/71 drive families — Premium and Quantum gave way to the Modicon M580, the ATV61/71 to the Altivar Process ATV630/930 generation. The installed base did not retire with them. Water plants, mines, cement works and building services still run TSX Premium racks, Quantum hot-standby pairs and ATV71 drives every day, and when something fails, the spare has to come from the sourcing market. Schneider references are precise, but only if you read them completely.
Read note →2026-10-31
The drive is dead and the spare is on its way. The hour before it arrives decides whether the line runs tonight or kills the new drive by Friday. Fault codes before power-cycling, parameters before unplugging, and the cause before the swap — in that order.
Read note →2026-10-31
The part arrived shrink-wrapped and labelled new. That proves almost nothing. This inspection guide works from the outside in — packaging, date codes, screw marks, board evidence — and ends with what no bench test can tell you, so you know what to ask before you pay.
Read note →2026-10-31
The label on a failed module carries three or four different numbers, and only one of them identifies the part. This field guide shows which string matters for each major brand, which suffixes change the hardware, and what to photograph before the label gets any worse.
Read note →2026-10-28
Discontinued PLCs, drives and HMIs keep factories running long after the makers stop selling them. A practical sourcing playbook: specification, condition grades, cross-references and red flags.
Read note →2026-10-28
PLC-5 and SLC 500 systems were discontinued by Rockwell, but the installed base is huge. How to specify, check and source 1785 and 1746/1747 spares without downtime surprises.
Read note →2026-10-28
SIMATIC S5 and early S7 modules are long out of production but still running plants worldwide. What to check before you order, and how INDPRT sources legacy Siemens parts.
Read note →2026-06-09
Price is only one line. Condition, validity and freight decide whether the offer is usable.
Read note →2026-05-18
Traders and plants often need PLCs, sensors and pneumatics from different makers in one enquiry.
Read note →2026-04-02
Hard-to-find PLC and I/O modules need extra checks before you compare price alone.